It’s too early to say whether the B.C. Hydro Site C project can be completed on time and on budget, according to a preliminary report from the B.C. Utilities Commission.
In its report on the $8.8-billion hydro-power project, filed late Wednesday to meet a provincial government deadline, the Commission said the project is currently on time and, indeed, has a year’s worth of contingency time built in. It says B.C. Hydro appears to be pushing ahead more aggressively than planned and if it experiences no delays, it could be producing power a year ahead of schedule, in 2023.